Start with the date the material is needed for use or onward distribution. Work back through warehouse receipt, port release, the sailing and order preparation to identify the order-confirmation target. Use the checklist to put dates, contacts and open decisions in one plan.

Agree the goods-ready date and dispatch window with Bergano for the specific order. Coordinate transport dates with the party arranging freight, and receiving requirements with your importer, broker and warehouse.

Set the destination and receiving window

Record:

  • Product grade and intended use, with quantity per SKU.
  • Destination port and warehouse city.
  • Who arranges ocean freight, origin transport and inland delivery.
  • Date the material is needed for use or onward distribution.
  • Time your team needs for unloading, incoming inspection and release for use.
  • Earliest, preferred and latest acceptable warehouse receiving dates.
  • Any warehouse closure dates or required unloading appointment.

For repeat orders, include your next receiving window. For a mixed-product container, identify the items that must travel together and any approval still open for each item. Choose the grade using our sodium bicarbonate product range.

Build one shared milestone plan

Start with your receiving requirements, then check the preceding milestones with the relevant contacts. These are planning checkpoints, not fixed waiting periods. Some work can run in parallel.

Copy the blank table and complete it with your team. Use a separate row for dates that differ, including cargo and document cut-offs. Record the time zone when a cut-off includes a time.

Use these date labels:

  • Target: a requirement your team wants to meet.
  • Estimate: a current forecast, including vessel ETD and ETA.
  • Agreed action deadline: a specific action or deadline accepted by the relevant party.
  • Actual: a completed event with its recorded date.

An ETA remains an estimate when it appears on a booking confirmation. Keep the date source and last check beside it. Record actual departure and arrival dates when the events have occurred.

Milestone, working backwards Date or window, with time zone Date label Coordination contact Prerequisite or open item Source and last checked
Material available for use or distribution ___ ___ ___ Warehouse receipt and required acceptance checks ___
Warehouse receipt ___ ___ ___ Inland transport, unloading slot and receiving equipment ___
Port release and collection ___ ___ ___ Shipment-specific documents, customs and carrier/terminal release arrangements ___
Vessel arrival at destination port ___ Estimate / Actual ___ Current sailing and any transshipment ___
Vessel departure ___ Estimate / Actual ___ Booking and shipment cut-offs ___
Cargo cut-off for the selected service ___ ___ ___ Goods ready and origin transport ___
Shipping-instruction or other document cut-off ___ ___ ___ Information required by the booking party ___
Dispatch from the agreed origin location ___ ___ ___ Goods ready and agreed collection/transport arrangement ___
Goods ready for dispatch ___ ___ ___ Order requirements and packing/label decisions ___
Order confirmation ___ ___ ___ Grade, specification, quantity and open approvals ___
Copyable plain-text milestone plan

Enter the person coordinating each checkpoint for this shipment. The table records working contacts; the agreed transport scope determines each party’s obligations.

Vessel arrival, cargo release, warehouse receipt and availability for use are distinct milestones. Confirm release and collection requirements with the importer, broker and logistics contacts for the shipment.

Attach approvals to the dates they affect

For each open approval or document, record:

  • Item to complete.
  • Contact responsible for the action.
  • Milestone it must precede.
  • Required date and current status.

Agree the specification and any sample-review requirements with your quality team. Set packing and label deadlines before the work that relies on them. Identify shipment documents and the dates their recipients need them. Plan document preparation and delivery alongside the shipment; do not assume every final document exists before order confirmation.

For shipments to Vietnam, see our packing and receiving guide and product and shipment document guide.

Check gaps before confirming the plan

Ask each contact for the timing of their stage and any allowance needed between stages. Keep that allowance visible, with the reason and person who supplied it; do not apply a fixed number of days to every route.

If the dates do not fit, identify the affected checkpoint and ask its contact about alternatives. Review linked dates and open approvals together. Keep the latest plan, the date it was checked and the next review point.

Send your timing request

Copy these fields into your enquiry:

  • Product grade and intended use:
  • Quantity per SKU; items sharing a container:
  • Packing format and pallet requirements, if decided:
  • Destination port and warehouse city:
  • Who arranges ocean freight, origin transport and inland delivery:
  • Required date for use or onward distribution:
  • Earliest / preferred / latest warehouse receiving date:
  • Approvals or document requirements still open:
  • Next receiving window for repeat orders: